https://en.arctic.ru
Rosatom plans to invest 65 billion rubles in shipyard construction in Murmansk
Rosatom plans to invest 65 billion rubles in shipyard construction in Murmansk
Arctic.ru: Discover how Russia implements its development goals in the Arctic and the Far East
2026-10-23T13:45
2026-10-23T13:45
2026-10-23T16:37
news
murmansk region
infrastructure
/img/07e9/09/1e/1050436_0:161:3071:1888_1920x0_80_0_0_f74433e099ff933546eca02d9cf36ec8.jpg
The new shipyard is planned for a site between the Murmansk-17 facility and the Mokhnatkina Pakhta wharf area. Its infrastructure is expected to enable the localization of production of high-tech marine equipment previously assembled using foreign manufacturing facilities.According to procurement documents, 51.5 billion rubles is earmarked for design and construction, with another 13.5 billion allocated for equipment supplies.The funding will also cover the preparation of design and cost-estimate documentation; the supply, installation, and commissioning of equipment and engineering systems; obtaining all necessary permits to operate the facility; and construction of an access road, including a railroad crossing.Preparatory work and temporary structures are scheduled for completion between March and July 2027. The embankments are due to be completed by July and September 2028, respectively, and the workshop complex by April 2029.
https://en.arctic.ru/20260910/1747084.html
2026
Новости
ru-RU
https://en.arctic.ru/docs/about/copyright.html
https://xn--c1acbl2abdlkab1og.xn--p1ai/
/img/07e9/09/1e/1050436_171:0:2902:2048_1920x0_80_0_0_073ee234169dbd3403017e880729016c.jpgnews, murmansk region, infrastructure
Rosatom plans to invest 65 billion rubles in shipyard construction in Murmansk
The new shipyard is planned for a site between the Murmansk-17 facility and the Mokhnatkina Pakhta wharf area. Its infrastructure is expected to enable the localization of production of high-tech marine equipment previously assembled using foreign manufacturing facilities.
According to procurement documents, 51.5 billion rubles is earmarked for design and construction, with another 13.5 billion allocated for equipment supplies.
The funding will also cover the preparation of design and cost-estimate documentation; the supply, installation, and commissioning of equipment and engineering systems; obtaining all necessary permits to operate the facility; and construction of an access road, including a railroad crossing.
Preparatory work and temporary structures are scheduled for completion between March and July 2027. The embankments are due to be completed by July and September 2028, respectively, and the workshop complex by April 2029.