New power transmission lines with a total length of 17.62 kilometers will be built in Salekhard, Labytnangi, Novy Urengoi, as well as in the Shuryshkarsky, Tazovsky and Priuralsky districts. Nine new transformer substations will be installed in Labytnangi, Noyabrsk, the Priuralsky and Tazovsky districts, as per the press service of the Government of the Yamal-Nenets Autonomous Area.There are plans to overhaul multiple operational facilities, including over 16 kilometers of power grids in Noyabrsk, Novy Urengoi, the Yamasky,Tazovsky and Priuralsky districts, as well as 14 transformer substations in Labytnangi and communities in the Priuralsky, Purovsky and Shuryshkarsky districts.There are also plans to overhaul over 13 kilometers of networks in 13 communities, as well as 16 substations in eight territories.During the summer season, power workers will conduct preventive maintenance of 37 pieces of basic power-generating equipment.The works will be conducted in accordance with investment and repair programs.
https://en.arctic.ru/20260319/1327045.html
2026
Новости
ru-RU
https://en.arctic.ru/docs/about/copyright.html
https://xn--c1acbl2abdlkab1og.xn--p1ai/
/img/07ea/01/1b/1071714_173:0:2904:2048_1920x0_80_0_0_4c172cdbe277d24cd1af0f9fd8b1ddf0.jpgnews, yamal-nenets autonomous area, infrastructure
Yamal approves plans for building and modernizing the power supply system for 2026
New power transmission lines with a total length of 17.62 kilometers will be built in Salekhard, Labytnangi, Novy Urengoi, as well as in the Shuryshkarsky, Tazovsky and Priuralsky districts. Nine new transformer substations will be installed in Labytnangi, Noyabrsk, the Priuralsky and Tazovsky districts, as per the press service of the Government of the Yamal-Nenets Autonomous Area.
There are plans to overhaul multiple operational facilities, including over 16 kilometers of power grids in Noyabrsk, Novy Urengoi, the Yamasky,Tazovsky and Priuralsky districts, as well as 14 transformer substations in Labytnangi and communities in the Priuralsky, Purovsky and Shuryshkarsky districts.
There are also plans to overhaul over 13 kilometers of networks in 13 communities, as well as 16 substations in eight territories.
During the summer season, power workers will conduct preventive maintenance of 37 pieces of basic power-generating equipment.
The works will be conducted in accordance with investment and repair programs.